Spring (March - May)
Colder temperatures reduce penetration and can slow the curing process significantly, adding up to a week, or 14 days in all, to fully cure.
Application is not recommended below 55 degrees F ground temperature, or when there is a risk of freezing within 72 hours.
Light, straight traffic can begin immediately after compaction. Turning traffic, overnight parking, dirt bikes, UTVs, forklifts and farm equipment should wait until the millings have cured into a hard, durable surface.
Rain: millings can be moist, but not soggy, at the time of application. Millings are very porous, and rain will typically drain through them after a few hours. Avoid applying HawkSeale solution if rain is likely within 4 to 6 hours of application.
Summer (June - August)
Summer delivers the best curing results thanks to warm temperatures and longer days. The heat helps HawkSeale penetrate and bond faster.
Extreme heat above 90 degrees F, especially combined with high humidity, can extend the full curing time to 3 to 4 weeks before the surface is ready for heavy turning trucks, overnight parking, dirt bikes, UTVs, forklifts and farm equipment.
Tip: Apply in early morning or late afternoon during heat waves to avoid the hottest part of the day.
Fall (September - November)
HawkSeale needs at least 72 hours without freezing risk after application. Typical cure time is 2 to 14 days at 65 to 85 degrees F.
Tip: Check the 10-day forecast before starting. You want at least 3 dry days with temperatures above freezing.
Winter (December - February)
Not recommended in northern climates. Frozen ground and low temperatures lead to poor penetration and curing.
We do ship to southern climates where winter temperatures stay above 50 degrees F, with no risk of freezing during delivery or after application.
Pre-Application Checklist
- Ground temperature above 55 degrees F
- No rain expected for 4-6 hours after application
- Wind under 15 mph
- Surface is dry and free of standing water
- Millings are graded to 3 to 4 inches deep (depth can vary from 2 to 5 inches)
- Depths of 6 to 8 inches should be built in 2 layers